Flood Damaged Road Repair Schedule
Last modified: November 11, 2009 - 2:10 PM
Flood Damage Repair Schedule - Last Updated 2:15pm 26/10/2009.
The list below is of major work required as a result of the 2009 floods.
| Street Name | Location | Status | Anticipated Repair Schedule |
| Timboon Road | Gleniffer/Hydes Creek | Landslip Restoration - Survey completed, options being assessed. | October 2009 |
| Short Street Lane | Bellingen | Landslip Restoration - Tender awarded for repair work | Completed - 23 October 2009 |
| Crown Street | Bellingen | Culvert Replacement - Options being assessed | December 2009 |
| Coronation Street | Bellingen | Landslip Restoration - Options being assessed | February 2010 |
| Darkwood Road | Darkwood | Replacement of Justins Bridge - Design work commenced | |
| South Arm Road | Urunga | Landslip Restoration | Options being assessed |
| Summervilles Road | Gordonville | Culvert Restoration - Design work commenced |