 Timboon Road  Gleniffer/Hydes Creek  Landslip Restoration - Survey completed, options being assessed.  October 2009
 Short Street Lane  Bellingen  Landslip Restoration - Tender awarded for repair work  Completed - 23 October 2009
 Crown Street  Bellingen  Culvert Replacement - Options being assessed  December 2009
 Coronation Street  Bellingen  Landslip Restoration - Options being assessed  February 2010
 Darkwood Road  Darkwood  Replacement of Justins Bridge - Design work commenced  
 South Arm Road  Urunga  Landslip Restoration  Options being assessed
 Summervilles Road  Gordonville  Culvert Restoration -  Design work commenced  