Cut Bank Bridge Replacement

  • Project typeReplacement
  • Project value$2,872,025
  • Project scheduleImplement
  • Contractor nameWaeger Bridge Constructions
Image of Cut Bank Bridge before replacement

About the Project & Funding

Bellingen Shire council has secured $2,297,620 in funding for the replacement of Cut Bank Bridge on Tyringham Road through the Australian Government’s Safer Local Roads and Infrastructure Program (SLRIP) and $574,405 from the Roads to Recovery Program (RTR). The total project cost is $2,872,025.

The SLRIP has been created to support the delivery of safer and more productive roads across Australia.  The Roads to Recovery Program supports the construction and maintenance of local road assets to facilitate improved accessibility and safety. The replacement of Cut Bank Bridge will improve the safety and functionality of Tyringham Road, ensuring it remains a reliable and accessible route during emergencies and natural disasters.

Scope of Works

The project will replace the existing Cut Bank Bridge on the Bellingen River located at low-level crossing over Cut bank Creek. The existing bridge is an aging timber structure nearing the end of it’s serviceable life and will be replaced with concrete structure that will provide increased flood resilience to residents and maintain safety and a reliable crossing for road users. 

The new concrete bridge will be a 21-metre single-span, dual-lane concrete bridge.

A temporary access road will be constructed prior to demolition of the existing bridge to minimise disruption to traffic flow during the construction period, with only minor traffic stoppages anticipated.

The temporary access will be located on the upstream side of the existing bridge, will incorporate a 12-metre single-lane temporary bridge and traffic lights during construction.