Building 1 - (next to pool):
- Completion of concrete slab and footings: June 2025
- Completion of blockwork: July 2025
- Completion of roof: August 2025
- Completion and handover: December 2025
Building 2 - (next to Netball court) :
- Completion of concrete slab and footings: May 2025
- Completion of blockwork: June 2025
- Completion of roof: July 2025
- Completion and handover: November 2025